Pune Metro Line 3: Baner-Hinjewadi Corridor Update

Baner ramp opens for traffic as Hinjewadi-Shivajinagar metro corridor nears full completion in 2026.

Enquire Now

Published

Pune Metro Line 3 Progress: What's Happening on the Baner Stretch

Pune's most-watched infrastructure project, Metro Line 3 connecting Hinjewadi to Shivajinagar, is entering its final construction phase, and the Baner stretch is seeing visible movement on the ground. As per the latest PMRDA update, by the end of March 2026 the physical work of the project was about 94.58% complete and financial progress stood at 97.40%. This is a significant milestone for a corridor that has faced multiple timeline revisions over the years.

The 23.3 km line runs entirely elevated and will connect Hinjewadi with Shivajinagar's Civil Court through 23 elevated stations, developed by the special purpose vehicle Pune IT City Metro Rail Limited, a Tata Realty-Siemens joint venture. For residents and investors around Baner, five stations on this line fall in the immediate vicinity: Balewadi Phata, Baner Gaon, Baner, Krushi Anusadhan and Sakal Nagar, making this one of the best-connected micro-markets once the line is fully operational.

A key development for Baner residents is the integrated double-decker flyover running alongside the metro corridor. Construction of the ramps on the Shivajinagar and Aundh sides of the flyover was completed and opened for traffic on 20 August 2025. More recently, the Baner ramp opened for traffic on 8 March 2026, while work on the Pashan ramp is still in progress. This means commuters travelling between Baner and Shivajinagar are already experiencing reduced travel times on the road network, even before the metro itself becomes operational on this segment.

On the metro construction side, utility relocation work that often causes delays is nearly done. Shifting of electrical high voltage lines of 220 kV and 132 kV has already started, and the work of shifting other utilities is around 95% complete. This clears the way for final track and station finishing works along the Baner-Sakal Nagar-University stretch.

The project has been split into two operational phases for a phased rollout. Union Minister of State for Civil Aviation, Murlidhar Mohol, confirmed in July 2026 that the first operational section of Metro Line 3 will run from Maan in Hinjawadi to Balewadi, covering 13.3 km with 12 stations. This stretch, however, saw a short delay: the launch was postponed as the project awaited final technical and safety clearances from the Commissioner of Metro Railway Safety, whose team inspected the corridor between July 5 and July 9, 2026. Officials indicated the certification was expected shortly after, paving the way for commercial operations on the Hinjewadi-Balewadi leg.

Once that first leg opens, attention shifts squarely to the Baner-carrying stretch. Following the launch of the Hinjawadi-Balewadi section, construction efforts will shift to the remaining stretch between Balewadi and the District Court station in Shivajinagar. This is the segment that runs directly through Baner Gaon, Baner and Sakal Nagar stations, and its completion will finally give Baner residents a direct, elevated metro link to both the IT corridor in Hinjewadi and the civic and business hub in Shivajinagar.

At the state level, the project has strong political backing for further expansion. Maharashtra CM Devendra Fadnavis, speaking at the inauguration of Metro Bhavan in March 2026, said a 200-kilometre metro network will be developed in Pune in the coming years, considering the city's rapid growth, with instructions already given to Maha Metro to prepare a detailed expansion plan. He also noted that Pune Metro is receiving an encouraging response from citizens, with around 2.5 lakh passengers travelling daily, underlining the scale of demand this corridor is expected to absorb once fully operational.

For homebuyers evaluating Baner today, the message is clear: road infrastructure (the double-decker flyover) is already functional, utility works are almost complete, and the metro's first leg is going live in mid-2026, with the Baner-Shivajinagar leg to follow. This makes Baner one of the few Pune micro-markets where physical connectivity upgrades are visibly ahead of most competing locations, a factor that typically supports both rental demand and capital appreciation over the medium term.

Project

FAQs

What is the current status of Pune Metro Line 3 near Baner?
As per PMRDA's latest update, overall physical progress on the line stood at 94.58% by March 2026. The Baner ramp of the integrated flyover has already opened for traffic, while metro track and station works on the Balewadi-Shivajinagar stretch, which passes through Baner, are in the final construction phase.
Which metro stations will serve Baner directly?
Five stations on Line 3 serve the Baner area: Balewadi Phata, Baner Gaon, Baner, Krushi Anusadhan and Sakal Nagar, giving the locality dense metro coverage along the Mumbai-Bangalore Highway belt.
When will the metro through Baner become operational?
The first operational section, Hinjawadi to Balewadi (13.3 km, 12 stations), was targeted to open in mid-to-late July 2026 after final safety clearances. Construction will then shift to the Balewadi-District Court stretch covering Baner, which is expected to follow in subsequent months.
Has the double-decker flyover near Baner been completed?
Partly. The Aundh-Shivajinagar side ramps opened in August 2025, and the Baner ramp opened for traffic on 8 March 2026. Work on the Pashan ramp is still ongoing.
Who is building Pune Metro Line 3?
The 23.3 km elevated corridor is being developed by Pune IT City Metro Rail Limited, a joint venture between Tata Realty and Siemens, on a design-build-finance-operate-transfer (DBFOT) public-private partnership model.
How will this metro line benefit Baner homebuyers?
Once operational, residents will get a direct elevated link connecting Baner to the Hinjewadi IT hub on one side and Shivajinagar's civic and business district on the other, cutting current road commute times significantly during peak hours.
What was the original completion deadline for this project?
The project's original completion period was 40 months with a scheduled end date of 25 March 2025. Due to delays, the concessionaire was granted an extension, with the revised deadline pushed to 31 March 2026.
Is Pune's metro network expanding beyond Line 3?
Yes. The Maharashtra CM has announced plans for a 200-km metro network across Pune, with Maha Metro directed to prepare a comprehensive expansion plan, indicating sustained long-term investment in the city's mass transit infrastructure.
Does the metro connect to other existing Pune Metro lines?
Yes. Line 3 will interchange with the operational Purple Line and Aqua Line at the District Court (Civil Court) station in Shivajinagar, allowing seamless travel across Pune's metro network.
Is it a good time to invest in property near Baner given the metro progress?
With road infrastructure already functional and metro construction in its final stretch, Baner offers a rare window where physical connectivity is visibly improving ahead of full metro launch, a phase that historically supports steady price appreciation in Pune's growth corridors.

Birla Estates Projects

Anmol & Bhartiya Bhavan CHS Redevelopment
Upcoming

Anmol & Bhartiya Bhavan CHS Redevelopment

Khar West, Mumbai

3, 4, 5 BHK • Price on request

1.3-acre society redevelopment

BIRLA BHANDUP
Upcoming

BIRLA BHANDUP

Bhandup West, Mumbai

1, 2, 3 BHK • Price on request

New-launch homes in Central Mumbai

Birla Commercial Connaught Place
Upcoming

Birla Commercial Connaught Place

Connaught Place, Delhi

Office & retail shops • On request

Double-height retail and food court

Birla Connaught Place
Upcoming

Birla Connaught Place

Connaught Place, Delhi

Office Space, Retail Shops • Price on Request

30,000 sq ft commercial hub

Birla Dwarka Expressway
Upcoming

Birla Dwarka Expressway

Sector 37A, Gurugram

3, 4 BHK • Price on request

Pre-launch homes on the Dwarka Expressway corridor

Birla Estates Badarpur
Upcoming

Birla Estates Badarpur

Badarpur, South Delhi

2, 3 BHK • Price on Request

Upcoming Birla address on Mathura Road

Birla Estates Financial District
Upcoming

Birla Estates Financial District

Financial District, Hyderabad

2, 3 BHK • Price on request

Planned west Hyderabad residences

Birla Estates Greater Noida
Upcoming

Birla Estates Greater Noida

Sector 10 Greater Noida West, Greater Noida

2, 3, 4 BHK • Price on request

Upcoming homes near Kisan Chowk

Get In Touch

Fill in your details and we will reach out to you.

Back

Places in this story: Pune city guide · Hinjewadi area guide · Hinjawadi area guide

Shared for informational purposes only; nothing here is an offer or a contract. Plans, prices, and visuals are representative and may be updated at any time. Verify independently before you commit. About · Projects